[PDF][PDF] The Challenges to Assemble 100 Cryomodules for E-XFEL
C Madec, S Berry, P Charon, JP Charrier… - SRF2013 …, 2013 - accelconf.web.cern.ch
SRF2013, Paris, 2013•accelconf.web.cern.ch
Abstract As In-Kind contributor to the E-XFEL project, CEA is committed to the integration on
the Saclay site of the 101 cryomodules (CM) of the superconducting linac as well as to the
procurement of the magnetic shieldings, superinsulation blankets and 31 cold beam position
monitors (BPM) of the re-entrant type. The assembly infrastructure has been renovated from
the previous Saturne Synchrotron Laboratory facility: it includes a 200 m2 clean room
complex with 112 m2 under ISO4, 1325 m2 of assembly platforms and 400 m2 of storage …
the Saclay site of the 101 cryomodules (CM) of the superconducting linac as well as to the
procurement of the magnetic shieldings, superinsulation blankets and 31 cold beam position
monitors (BPM) of the re-entrant type. The assembly infrastructure has been renovated from
the previous Saturne Synchrotron Laboratory facility: it includes a 200 m2 clean room
complex with 112 m2 under ISO4, 1325 m2 of assembly platforms and 400 m2 of storage …
Abstract
As In-Kind contributor to the E-XFEL project, CEA is committed to the integration on the Saclay site of the 101 cryomodules (CM) of the superconducting linac as well as to the procurement of the magnetic shieldings, superinsulation blankets and 31 cold beam position monitors (BPM) of the re-entrant type. The assembly infrastructure has been renovated from the previous Saturne Synchrotron Laboratory facility: it includes a 200 m2 clean room complex with 112 m2 under ISO4, 1325 m2 of assembly platforms and 400 m2 of storage area. In parallel, CEA has conducted industrial studies and three cryomodule assembly prototyping both aiming at preparing the industrial file, the quality management system and the commissioning of the assembly plant, tooling and control equipment. In 2012, the contract of the integration has been awarded to ALSYOM. The paper will summarize the outputs of the preparation and prototyping phases and the status of the start of the industrial phase.