Interface and integration management for FPSOs

SF Yasseri, H Bahai - Ocean Engineering, 2019 - Elsevier
For the purpose of concurrent engineering, ease of fabrication, time to first oil and reduction
of onsite special competencies, the topside of FPSO is divided into several modules …

System readiness level estimation of oil and gas production systems

S Yasseri, H Bahai - International Journal Of Coastal, Offshore And …, 2018 - ijcoe.org
This paper explores further and describes the System Readiness Level estimation for means
of production in the oil and gas industry, through a case study. The concept as Technology …

Availability assessment of subsea distribution systems at the architectural level

SF Yasseri, H Bahai - Ocean Engineering, 2018 - Elsevier
This paper presents a framework for the availability assessment of subsea distribution
systems during the functional design (selection) phase. This framework, which also includes …

Leveraging epoch‐era analysis and digital twin for effective system concept and execution: A CO2 storage salt‐cave project

DP Vieira, ÍA Fonseca, K Nishimoto… - Systems …, 2023 - Wiley Online Library
With the demand to reduce the release of CO2‐rich gases into the atmosphere, the offshore
industry is turning to systems for gas capture and storage. The construction of a cave for that …

Application of a System Engineering Framework to the Subsea Front‐End Engineering study

S Engen, K Falk - INCOSE International Symposium, 2018 - Wiley Online Library
This article applies formal system engineering methods in early‐phase concept studies in
the subsea oil and gas industry to identify early‐phase needs, and reduce late‐phase …

Interface management of subsea field development

S Yasseri - Underwater Technology, 2015 - ingentaconnect.com
An interface refers to any logical or physical relationship required to integrate the
boundaries between subsystems or between subsystems and their environment. The …

A measure of subsea systems' readiness level

SF Yasseri - Underwater Technology, 2016 - ingentaconnect.com
Systems readiness level (SRL) is a metric for assessing progress in developing major
subsea systems. SRL methodology builds on technology readiness levels (TRLs) …

Reliability assurance of subsea production systems: a systems engineering framework

S Yasseri, H Bahai, R Yasseri - International Journal Of Coastal, Offshore …, 2018 - ijcoe.org
​ Due to the high investment costs for deep-water subsea production systems of high-value
subsea fields, it is crucial to ensure a high availability to recover the investment. The …

Evidence-based practice in subsea engineering

S Yasseri - Underwater Technology, 2015 - ingentaconnect.com
Engineers are often called to deal with situations for which there is no precedence or a
known solution. They rely on their expertise to make decisions, and in some cases the …

[PDF][PDF] Rationality for Engineers: Part I-Setting the scene

S Yasseri - International Journal Of Coastal, Offshore And …, 2021 - ijcoe.org
The truly complex element of modern times is not the technology, but the engineers who
develop, design, manufacture, and maintain it. An engineer's job is to change/improve …